Phase 1, Stage 7 Progress Report
progress pictures
0f 2001+2002
progress pictures 0f
2003
Click on picture to enlarge it. Use the back button to get back to this
page or open in a new window.Or it may open in a new window. Just close
it.
Below progress pictures of 2004
March 2004 we excavated to a near final bed level. We
continued the work we started last year, levelling the canal to the final
level under the canal bridge.
 |
 |
 |
 |
| March 2004: We excavated under
the bridge and it is ready for lining. |
April 2004:
We have laid up to the bridge and concreted.
|
We have started to excavate and profile
the underwater shelf. |
MAY 2004
We have started the Gabion walls and the construction of the
underwater shelf. |
 |
 |
 |
 |
MAY 2004
We have excavated from the bridge, |
July 2004:
We have excavated up to the underwater shelf. |
July 2004:
KESCRG cuting lengths of Bentomat.
|
KESCRG have cut a lot of bentomat for the August week. |
WAT & BITM August Canal Camp 2004
The main aim of the August Camp was to
have an onslaught of laying bentonite and concreting.
We were taking delivery of 10 to 11 lorries a day of concrete, each
lorry containing roughly 4.5 cubic metres of concrete.
 |
 |
 |
 |
AUG 2004
We have excavated the old road up to the tip and profiled the rest of
the underwater shelf. |
This is the finished underwater shelf. The gabion is
being constructed. |
We have started the excavation of the winding hole. |
We have started the lining of the canal with bentomat
and started to put concrete on top of it. |
 |
 |
 |
 |
| From the bridge to the winding hole has all been lined
and concreted. |
This is more lining and concreting approaching the
winding hole. |
This is a shot towards the winding hole. We have the
winding hole to do plus another 100 metres after that. |
In this picture, you can see us attaching the bentonite
to the wall and rolling it out ready for concreting. |
 |
 |
 |
 |
| Sep 2004: We did a pour of concrete and excavation went
on |
Excavation near the end |
Oct 2004: we have cut all the lengths of bentomat and
started lining. |
The excavator is lifting bentomat into place for us. It
is much easier than us moving it by hand!! |
 |
 |
 |
 |
| Nailing the bentomat to the wall and pulling it into
shape. |
Oct 2004: after we had laid the bentomat, we started
concreting. The main bit of the winding hole is complete. |
Nearly finished. Just one more pour of concrete to go. |
The last pour of Phase 1. |
 |
 |
 |
 |
| The WAT volunteers hard at work spreading the concrete, |
Oct 2004: All concreting is done and Phase 1 is nearly
complete. Just a bund to go at the end. |
All that is left is the bund and filling it with water. |
The main completed winding hole. |
Return to Phase1
Return to Phase 1, Stage 7
Return to Index