Phase 1, Stage 7 Progress Report

progress pictures 0f 2001+2002

progress pictures 0f 2003

Click on picture to enlarge it. Use the back button to get back to this page or open in a new window.Or it may open in a new window. Just close it.

Below progress pictures of 2004

March 2004 we excavated to a near final bed level. We continued the work we started last year, levelling the canal to the final level under the canal bridge.

{short description of image} {short description of image} {short description of image} {short description of image}
March 2004: We excavated under the bridge and it is ready for lining. April 2004:
We have laid up to the bridge and concreted.
We have started to excavate and profile the underwater shelf. MAY 2004
We have started the Gabion walls and the construction of the underwater shelf.
{short description of image} {short description of image} {short description of image} {short description of image}
MAY 2004
We have excavated from the bridge,
July 2004:
We have excavated up to the underwater shelf.
July 2004:
KESCRG cuting lengths of Bentomat.
KESCRG have cut a lot of bentomat for the August week.

WAT & BITM August Canal Camp 2004

The main aim of the August Camp was to have an onslaught of laying bentonite and concreting.

We were taking delivery of 10 to 11 lorries a day of concrete, each lorry containing roughly 4.5 cubic metres of concrete.

{short description of image} {short description of image} {short description of image} {short description of image}
AUG 2004
We have excavated the old road up to the tip and profiled the rest of the underwater shelf.
This is the finished underwater shelf. The gabion is being constructed. We have started the excavation of the winding hole. We have started the lining of the canal with bentomat and started to put concrete on top of it.
{short description of image} {short description of image} {short description of image} {short description of image}
From the bridge to the winding hole has all been lined and concreted. This is more lining and concreting approaching the winding hole. This is a shot towards the winding hole. We have the winding hole to do plus another 100 metres after that. In this picture, you can see us attaching the bentonite to the wall and rolling it out ready for concreting.
{short description of image} {short description of image} {short description of image} {short description of image}
Sep 2004: We did a pour of concrete and excavation went on Excavation near the end Oct 2004: we have cut all the lengths of bentomat and started lining. The excavator is lifting bentomat into place for us. It is much easier than us moving it by hand!!

{short description of image} {short description of image} {short description of image} {short description of image}
Nailing the bentomat to the wall and pulling it into shape. Oct 2004: after we had laid the bentomat, we started concreting. The main bit of the winding hole is complete. Nearly finished. Just one more pour of concrete to go. The last pour of Phase 1.

{short description of image} {short description of image} {short description of image} {short description of image}
The WAT volunteers hard at work spreading the concrete, Oct 2004: All concreting is done and Phase 1 is nearly complete. Just a bund to go at the end. All that is left is the bund and filling it with water. The main completed winding hole.