Phase 1, Stage 7 Progress Report
Click on picture to enlarge it. Use the back button to get back to this page or open in a new window.Or it may open in a new window. Just close it.
To see an archive of the pictures of the work on this stage, click here
![]() |
|
| June 2001: This temporary road will eventually be dug out to form the canal bed. | AUG 2003 We have laid about 26 metres of bentomat. |
March 2004 we excavated to a near final bed level. We continued the work we started last year, levelling the canal to the final level under the canal bridge.
WAT & BITM August Canal Camp 2004
The main aim of the August Camp was to have an onslaught of laying bentonite and concreting.
We were taking delivery of 10 to 11 lorries a day of concrete, each lorry containing roughly 4.5 cubic metres of concrete.
![]() |
![]() |
| July 2004: We have excavated up to the underwater shelf. |
AUG 2004: This is a shot towards the winding hole. We have the winding hole to do plus another 100 metres after that. |
![]() |
![]() |
| Oct 2004: we have cut all the lengths of bentomat and started lining. | Oct 2004 The main completed winding hole. |