Phase 1, Stage 6 Progress
Report
(22.07.2002)
Click on picture to enlarge it. Use the back button to get back to this page or open in a new window. Or it may open in a new window. Just close it.
Stage 6 is the footpath wall between the lock and the bridge. After
setting out the line of the wall, excavation commenced and exposed the
original canal wall. (see picture below) BW project Engineer, John
Kearsey, has now decided that the old wall must be removed and a new wall
built in its place.