Phase 1, Stage 7 Progress in 2003
April 2003 we excavated to a near final bed level between the old stop lock and the bridge and for the blinding under the bridge. In August 2003 we had a 5-day work party, taking our first delivery of bentomat rolls.Over these days, we had a learning curve on laying and defining a method of doing this